The Harlo Update 05/10/16

Elevator core at 1350 Boylston Street tops off


1350 Boylston Street's elevator core has topped off. At the top of the elevator core is a decking system that was used to frame pouring of concrete to construct the core.


1350 Boylston Street's topped-off elevator core. Note decking at top of core.


View of 1350 Boylston Street's elevator core from nearby Pierce Boston


Construction of 1350 Boylston Street's 17-story steel superstructure has begun. The first pieces of superstructure steel have been installed at the building's base.


Vertical pieces of superstructure steel installed at 1350 Boylston Street


View of rising steel superstructure (center) with respect to elevator core (left) and sheet pile wall (right)


At the base of the parking structure, the construction team is assembling a PERI Skydeck system that will be used to frame pouring of concrete to construct 1350 Boylston Street's superstructure. A similar system is being used to build Pierce Boston, a 30-story tower also under construction in the Fenway neighborhood.



At the parking structure's base are the walls and yellow beams used to build the Skydeck system


Concrete for 1350 Boylston Street's mat foundation has been poured at the base of the parking structure. Additional foundation concrete is now being poured vertically along the sheet pile wall. With foundation concrete poured and superstructure construction underway, 1350 Boylston Street's horizontial foundation support system will soon be dismantled.



View of foundation support system extending horizontially across the poured foundation


View of foundation concrete poured vertically along the sheet pile wall up to the horizontal foundation support system. Concrete will be poured along the entire sheet pile wall following dismantling of the support system.


View of foundation support system against sheet pile wall


View of foundation support system against sheet pile wall


More information about 1350 Boylston Street is posted below.


Feb 20, 2016

Tower crane installed at 1350 Boylston Street


A tower crane has been installed at 1350 Boylston Street, signaling the impending start of elevator core and superstructure construction. When we arrived at 1350 Boylston Street, tower crane installation had just been completed. The crane used to build the tower crane was parked on site.


View of completed red tower crane (right) beside the white crane (left) used to build the tower crane

A second smaller white crane was also present, presumably to lift the excavators out of the nearly fully excavated parking structure.



At right is the larger white crane used to build the tower crane. At left is the smaller white crane, which has presumably just lifted the yellow excavator beside it out of the parking structure.


View of both white cranes along Boylston Street


View of white crane securing system


Excavation of 1350 Boylston Street's foundation and parking structure is almost complete. Foundation concrete will soon be poured along the sheet pile wall and the base of the parking structure.


An excavator at the base of the nearly fully excavated foundation. Along the perimeter of the foundation is a sheet pile wall horizontally reinforced by a foundation support system.

View The Harlo >>

Search BLDUP

Search BLDUP for news, projects, and companies to find the information that pushes your business forward.

Related News