345 Harrison officially breaks ground
We had the honor and privilege of attending the official 345 Harrison groundbreaking ceremony this past Wednesday, May 25th. We would like to extend huge congratulations and thanks to UDR on this important milestone. 345 Harrison will further enliven the rapidly developing South End New York Streets neighborhood with hundreds of new residents in addition to new retail space. Above and below are the latest renderings of 345 Harrison.
Nighttime view of 345 Harrison from Traveler Street towards Downtown Boston
View of 345 Harrison at corner of Harrison Avenue (right) and Traveler Street (left)
View of 345 Harrison at corner of Traveler Street (right) and Washington Street (left)
Speakers at the 345 Harrison groundbreaking ceremony included UDR Vice President of Development Robert McCullough, UDR Development Associate Elizabeth Likovich, City of Boston Chief of Civic Engagement Jerome Smith, CBT Architects Principal David Hancock and John Moriarty & Associates CEO David Leathers.
UDR Vice President of Development Robert McCullough
UDR Development Associate Elizabeth Likovich
City of Boston Chief of Civic Engagement Jerome Smith
CBT Architects Principal David Hancock
John Moriarty & Associates CEO David Leathers
Speeches were followed by a ceremonial groundbreaking on the construction site.
Shovels about to fly at 345 Harrison
Shovels fly at 345 Harrison
UDR development team
CBT Architects team
View of the ceremonial groundbreaking tent
Pile driving and excavation are underway at 345 Harrison. A large section of the project’s sheet pile wall is in place. The sheet pile wall will reinforce 345 Harrison’s foundation and underground parking garage. Two new buildings will be built at 345 Harrison.
Excavators parked along a section of 345 Harrison's sheet pile wall
View of 345 Harrison sheet pile wall along Harrison Avenue (right) towards Downtown Boston
View of 345 Harrison sheet pile wall construction facing Harrison Avenue and Ink Block
Concrete piles are being driven for additional structural support. Approximately 650 concrete piles will be driven at 345 Harrison. A number of H piles will also be driven. A number of piles have been driven along the north side of the project site fronting William Mullins Way. Pre-trenching is underway to remove debris and stone and prepare the south side of the site fronting Traveler Street for pile driving.
Concrete pile driving underway at the corner of Harrison Avenue and William Mullins Way
View of pile driving at 345 Harrison including concrete piles, H piles and sheet piles
The 345 Harrison construction team drives concrete piles along Harrison Avenue
Pre-trenching underway at the south side of 345 Harrison
Excavation of 345 Harrison’s underground parking garage is well underway. A one-level underground garage with parking for 275 cars and 325 bicycles will be built along William Mullins Way. Approximately 10 more vertical feet will be excavated prior to the garage’s completion.
View of partially excavated section of 345 Harrison's underground parking garage along William Mullins Way looking towards Harrison Avenue
UDR is looking for suggestions for potential names and building amenities for 345 Harrison. Tweet your suggestions with #Lovefor345Name and #Lovefor345Amenity, respectively, and you could win up to $10,000!
UDR #Lovefor345 graphic
345 Harrison is expected to open in early 2018. Pre-leasing of residences at 345 Harrison has begun, visit UDR’s 345 Harrison page for more information and to join the interest list. A live camera has been installed showing progress at 345 Harrison. More information about 345 Harrison is posted below.
The following are photographs of 345 Harrison taken earlier in May showing excavation and sheet pile driving underway:
Panoramic view of 345 Harrison site from corner of Washington Street and William Mullins Way
Panoramic view of 345 Harrison site from corner of Harrison Avenue and William Mullins Way
View of excavation underway in background and sheet piles ready for driving in foreground