Mosaic on the Riverway Update 06/22/16

Exterior shell of Mosaic on the Riverway is sealed, condos over 95% sold


Installation of windows at Mosaic on the Riverway is complete, and the exterior of the building is completely sealed from the elements. Exterior finishes are nearly fully installed, and installation of interior finishes is underway. Per the Mosaic on the Riverway project website, condominiums are over 95% sold with one remaining. Mosaic on the Riverway will contain a mix of homeownership condominiums and rental apartments.


Mosaic-on-the-Riverway-1
Looking west on Fenwood Road

Mosaic-on-the-Riverway-4
View from Riverway

Mosaic-on-the-Riverway-7
View from Riverway

Mosaic-on-the-Riverway-10
View from Brookline Avenue

Mosaic-on-the-Riverway-9
View from Riverway


USG Securock Sheathing (green) and Carlisle Waterproof Coating (blue) are installed along the Mosaic on the Riverway facade, providing a moisture and mold resistant air/water barrier system. Exterior finish panels are being installed along the facade using a pulley system anchored at the roofline. VMZINC facade application material is being used to affix finish panels.


Mosaic-on-the-Riverway-3
South corner of building

Mosaic-on-the-Riverway-2
East corner of building

Mosaic-on-the-Riverway-8
Pulley system anchored on roof

Mosaic-on-the-Riverway-5
Crates of VMZINC facade material

Mosaic-on-the-Riverway-12
Installation of facade


Work is underway on sidewalks and curbing surrounding Mosaic on the Riverway.


Mosaic-on-the-Riverway-11
Workers curbing out the project

Mosaic-on-the-Riverway-6
Excavation rigs and telescoping forklift


More information about Mosaic on the Riverway is posted below.