Encore Boston Harbor Update 10/11/16

Wynn Boston Harbor excavation underway, slurry wall nearing completion


Treviicos has nearly completed Wynn Boston Harbor’s slurry wall. Trenches for the wall’s final sections are being excavated using slurry wall rigs with hydromill and grab excavators. Steel reinforcement cages have been installed in excavated slurry wall trenches that range from 50 to over 120 feet deep. Treviicos is hard at work pouring concrete into installed reinforcement cages to complete the slurry wall.


Slurry wall sections have been excavated where concrete has been poured, exposing the hardened concrete. Following excavation, a cap beam, an extra layer of concrete, has been poured above the slurry wall to continue the foundation. J. Derenzo Companies is at work excavating both the slurry wall and Wynn Boston Harbor’s 3,000 car underground parking garage.


Completion of the garage is anticipated before the end of the year, at which point construction of the 3 million square foot casino’s 24-story, 350 foot tall steel frame will begin. Structural pile driving is now underway to support the future casino. The following is a video tour of Wynn Boston Harbor's slurry wall by Treviicos' David Gazda:



The following are photographs of the Wynn Boston Harbor construction site:


Slurry Wall
Wynn Boston Harbor Slurry Wall


Excavation
Wynn Boston Harbor Excavation


Slurry Wall Concrete Pouring
Wynn Boston Harbor Concrete Pouring


Slurry Wall Construction Equipment
Wynn Boston Harbor Slurry Wall Equipment


Driven Piles
Wynn Boston Harbor Driven Piles