Parcel K Update

02/12/19


Framing Nearly Complete for Parcel K as Exterior Work Kicks Off

Structural framing for the upcoming mixed-use project at Parcel K in the Seaport is nearly complete and exterior work has started. The 500,000 square foot project is comprised of two buildings, both 12 stories, one a Hyatt Place hotel, the other a rental project. The hotel will feature 294 rooms while the rental building will include 304 apartments. The buildings will also contain around 12,000 square feet of office space and approximately 18,000 square feet of retail and restaurant space. A one-level underground parking garage will have the capacity for approximately 450 cars.

Construction is expected to be complete in Spring 2020.

Parcel K February

 

Back to Parcel K >>

Related News

Parcel k seaport district boston 315 northern avenue mixed use residential retail project conroy development corporation massport arrorwstreet architecture rendering
Parcel K in Boston
Aug 16, 2018 - Site Work Begins at Parcel K in the Seaport
The viola
The Viola in Boston
Nov 04, 2015 - MassDOT officials approved a deal this week&nbs...