Boston University Goldman School of Dental Medicine Update 03/30/18

Traffic Signal and Handicap Access Work


Continued infrastructural work on the relocation of the traffic signal at the corner of Albany Street and East Newton Street. (Weekend work, as directed by the City of Boston, reduces the impact on traffic.) Eversource will be on-site to provide power to the temporary signal. The existing signal will remain active until the temporary signal is operational.

installation of the handicap lift at the School’s East Newton Street entrance will continue. Testing and State inspection will follow over the next week before the lift is officially available for public use. This is an important milestone as it will allow the existing handicap ramp to be taken offline and demolished to clear the way for the new addition’s footprint.

A tent will be set up on the construction site in the space between the School and the Newton Pavilion, and other preparations will be made for the project’s Groundbreaking Ceremony to be held on April 5.


Investigation of the routing of the building’s existing utilities will continue, and utilities presently serving the former cafeteria will be disconnected to prepare for its demolition in the coming weeks.

Construction personnel will continue to be on site (inside and out) to prepare for the cafeteria demolition and the start of construction of Phase 1 in the School’s basement and first floor.