Respected industry veteran Chris Berardi founded JDC Demolition Inc. as part of the J. Derenzo family of companies. Berardi’s solid reputation for excellence, technical expertise and repeat relationships with many of New England’s most regarded general contractors and property developers – coupled with the long-term financial stability of parent company J. Derenzo – have already helped the company achieve record growth.

Staffed by the most experienced operations team in New England, most of whom have worked together for decades, JDC Demolition offers clients the technical expertise required to complete projects safely and on schedule to pave the way for construction crews.

Notable recent projects include:

  • Burnham Building (former Filene’s building)
  • Salem State University Library
  • Salem Harbor Power Station
  • Merchant’s Row Quincy Redevelopment
  • Lesley University
  • Suffolk University 20 Somerset St.
  • Harvard University Bright Arena
  • Winsor School Performing Arts & Wellness Center
  • Pratt & Whitney

JDC Demolition emphasizes a collaborative approach to service to create long-lasting partnerships and are proud to count 90% of work from repeat clients.

 

Updates

BLDG 89
- May 27, 2020

$2M Plumbing & Gas Permits Pulled for Allston Mixed-Use Project Permits valued at over $2M have been pulled for the plumbing and gas install for BLDG 89 along Brighton Avenue in Allston. The upcoming mixed-use project will feature 129 apartments and 7,500 square feet of retail space. The development will also include 79 at-grade parking spaces and storage space for 138 bicycles.


BLDG 89
- Apr 29, 2020

Electrical Permit Issued for BLDG 89 in Allston An electrical permit valued at $870000.00 has been issued for the upcoming mixed-use project BLDG 89 along Brighton Avenue in Allston. The new building will feature 129 apartments ranging in size from studios through 2-bedrooms along with 3 ground floor retail spaces. 


BLDG 89
- Mar 05, 2020

Site Clear at for BLDG 89 in Allston Demo is complete and site work is now underway at 89 Brighton Ave. in Allston. The upcoming mixed-use project will feature 129 apartments with 7,500 square feet of retail space. The project will also include 79 parking spaces and storage space for 138 bicycles along with a transit screen in the lobby. 


BLDG 89
- Feb 07, 2020

Building Permit Granted for BLDG 89 A building permit valued at $27,459,696 has been pulled for BLDG 89, at 89-95 Brighton Avenue. The project will feature 129 apartments plus 7,500 square feet of ground-floor retail space.  79 at-grade parking spaces and storage space for 138 bicycles will also be located on-site.


BLDG 89
- Jan 06, 2020

Demo Permit Pulled for 95 Brighton Ave. A demo permit has been pulled to raze the existing structure at 95 Brighton Ave. in Allston the demo will make way for the approved mixed-use BLDG 89 project. The new project is set to feature 129 apartments plus 7,500 square feet of retail space. 79 at-grade parking spaces and storage space for 138 bicycles will also be located on-site.   


BLDG 89
- Nov 22, 2019

Permit Pulled to Cut Gas Service to 89 Brighton Ave. A permit has been issued to cut and cap the gas service to 89 Brighton Avenue in Allston in prep for demo. This demo would make way for the approved mixed-use project BLDG 89, to feature 129 apartments and 7,500 square feet of retail space. The project would also include parking for 79 cars and 138 bikes. Mike Samuels of Eden Properties tells BLDUP they expect to kick off demo shortly and plan to deliver units in the Spring of 2021.


No new thoughts. Inquire about becoming a thought leader by clicking here