Pile driving underway at AC Hotel South End
J. Derenzo Companies has completed initial excavation and pre-trenching at AC Hotel South End. Pile driving is now underway; precast concrete piles
averaging 100 feet long are being driven into the ground to provide structural support for the future AC Hotel South End building.
Pile driving rig
Precast concrete piles ready for driving
Partially driven piles
View of AC Hotel South End site looking towards Troy Boston
Pile driving rig (at left) with partially driven piles (at right)
Partially driven piles
Partially driven piles
Tips of shortened piles; piles at AC Hotel South End will average 100 feet long
More information about AC Hotel South End is posted below.
May 8, 2016
J. Derenzo Companies completes demolition, starts excavation at AC Hotel South End
J. Derenzo Companies’ JDC Demolition has fully demolished two former structures at the AC Hotel South End site, and demolition debris has been fully cleared. Work has begun on AC Hotel South End’s foundation; J. Derenzo Companies has started initial excavation and pre-trenching to prepare the site for pile driving.
View of AC Hotel South End site looking towards Downtown Boston
View of AC Hotel South End site looking towards Troy Boston
Backhoe (at left) and excavator (at right) used for initial excavation and pre-trenching