Foundation under construction at Portside at East Pier Phase Two, new renderings released
New structural piles have been driven at Portside at East Pier—Phase Two. The construction team is now pouring concrete on top of the new pile caps to build foundations for the project's two new buildings. A sheet pile wall has been installed surrounding the project site. Work continues on excavation of the buildings' underground parking structure.
New renderings recently released of the Portside at East Pier—Phase Two project can be found above. The following are photographs of Portside at East Pier Phase Two: