The Distillery Update 06/06/16

The Distillery tops off


The Distillery addition’s five-story superstructure has topped off and is sealed with a roof and windows. Exterior finish panels are being installed over sheathing and cladding.

Distillery-5
View of the Distillery addition along East 1st Street

Distillery-1
View of the Distillery addition's frontage along the project's future courtyard

Distillery-2
View of the Distillery addition from the corner of East 1st Street and H Street

Distillery-3
View of exterior finish installation underway at the Distillery addition

ZIP System R-Sheathing (green) is being used to insulate and seal the building. Georgia-Pacific Densglass Sheathing (yellow) is providing a mold-resistant barrier.

Distillery-6
View of sheathing and exterior finish installation underway along Dorchester Street

Distillery-7
View of sheathing and exterior finish installation underway along Dorchester Street