Portside at East Pier Phase Two Update 02/19/16

Foundation preparations are in full force at Phase Two of Portside at East Pier. W. L. French Excavating Corporation is performing initial earthwork, and J. F. White Contracting Company is driving concrete piles. Two buildings are under construction that will contain a total of 296 residential units.


   

   

   

   


Phase One of Portside at East Pier was completed in November 2014:



Expected completion of pile driving at Portside at East Pier—Phase Two is by April 2016. A total of 97 piles will be driven. Construction is expected to last roughly 30 months, with expected completion in Fall 2018.


Portside at East Pier—Phase Two is located at the intersection of Marginal and Bremen streets on the East Boston Waterfront.


Note: Cranshaw Construction has also begun work on Boston East, another East Boston Waterfront residential building.