Pier 4 Phase II
Update
03/04/16
Slurry wall foundation construction is beginning at Pier Four Phases Two and Three. Preparation for demolition of the former Anthony's Pier Four building on the Pier Four Phases Two and Three site has also begun.
Excavation of the Phase Two office building's foundation and construction of the building's slurry wall is expected to take approximately eight months. Afterwards, the office building's mat foundation will be poured, a process that will last under a month.