Halyard Update 10/07/20

Construction Continues at Halyard in Gloucester

Construction continues across the site at Halyard in Gloucester. The clubhouse exterior finishes are almost complete, and drywall is underway inside. Building 2 siding is well underway with windows and sliders complete and interior plumbing, electrical and mechanical rough installation is well underway. Building 1 roofing is complete and weather barrier installation is near completion with window and slider installation underway. Building 3 framing is near completion with the roof trusses being installed this week. In total the project will feature 200 modern apartments.
The Clubhouse is expected to be delivered in late November and the entire project to be complete by late Spring, 2021.

halyard october

Photo: Dolben

View Halyard >>