400 West Broadway Update 06/20/24

Drack Construction Management Nearing Finish Line on South Boston Project

17 months into construction, Drack Construction Management is rapidly nearing completion at 400 West Broadway in South Boston. Within the building, kitchen cabinets have been installed and finish carpentry is 80% complete on the residential floors. The passenger elevator installation is ongoing with a completion set for mid-July and mechanized parking for 34 cars is scheduled to start at the end of this month. On the exterior of the building the facade is 60% complete and expected to be finished by the end of July. The firm is on schedule to begin final inspections in August for the 47,000-square-foot mixed-use building which will include 36 residential units and 2 commercial spaces.