Fenway Center Update 08/14/18

Site Work Begins on Phase 1 of the Fenway Center

Site work is underway on Phase 1 of the Fenway Center in Kenmore Square.  This first phase of the $600 million project is set to include two residential buildings containing 312 units and around 37,000 sf of retail space.  Construction on Phase 1 is expected to be complete in early 2020. 
Three additinoal buildings will then be constructed for phase 2 including a 27 story mixed-use building, a 111K sf residential building and a parking garage.  In total the Fenway Center project will bring around 550 residential units, 160,000 sf of office space, and 50,000 sf of retail to the neighborhood.