Site Work Underway at Hingham's Broadstone Development
The month of May saw steady progress in site work and foundation placement. Bulk soil export and Zone 1 footing excavation were ongoing, while the installation of infiltration system #4 was completed. Approximately 40% of the exterior footings, 14% of the foundation walls and 20% of the column footings for Building 2 were placed. ACM abatement activities were close to completion.
The project is an upcoming multi-family apartment development located in Hingham, MA. It will consist of two buildings, both with four stories of wood framing above one level of post-tensioned podium parking.