Boston University Goldman School of Dental Medicine Update 03/29/18

Work Continues at the School’s East Newton Street Entrance

Construction of an overhead canopy at the East Newton Street entrance will begin. It will provide cover for pedestrians as they enter the building, as well as protection for the handicap lift. 

The reworking of the East Newton Street entrance vestibule will begin, including the construction of a temporary storage room, along with the slight relocation of the security desk in the vestibule.

The Boston Fire Department’s emergency connection to the building on the Albany Street side will be extended so that the connection point is outside of the construction fencing.

Investigation of the routing of the building’s existing utilities will continue, and utilities presently serving the former cafeteria will be disconnected to prepare for demolition in the coming weeks.

Construction personnel will continue to be on-site at the interior and exterior of the building to prepare for the cafeteria demolition and the start of construction of Phase 1 in the School’s basement and first floor.

View Boston University Goldman School of Dental Medicine >>

Search BLDUP

Search BLDUP for news, projects, and companies to find the information that pushes your business forward.

Related News