637 Main Street Overview
Last Update:
07/06/21
Address:
637 Main Street
Key Data, Images & News
Basic Details
Construction Cost
:
*************
PRO Data
Acquisition Purchase Price
:
*************
Related Projects (6)
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
View Related Projects With A BASIC Membership
When you upgrade, you get access to all Related Projects.
Related Documents (8)
BLDM0064242015
A permit for the amount of $5,510,549.00 was issued on 03/24/15 to Ownership.
Permit Details: Building 8 of 8 total buildings to be modernized (Building G, Stairways 21, 23, 25, 27, 29. & 31, 44 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building G (building 8 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 8 of 8 total buildings to be modernized (Building G, Stairways 21, 23, 25, 27, 29. & 31, 44 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building G (building 8 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064232015
A permit for the amount of $5,511,594.00 was issued on 03/24/15 to Ownership.
Permit Details: Building 7 of 8 total buildings to be modernized (Building C, Stairways 22, 24, 26, 28, 30 & 32, 47 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building C (building 7 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 7 of 8 total buildings to be modernized (Building C, Stairways 22, 24, 26, 28, 30 & 32, 47 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building C (building 7 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064222015
A permit for the amount of $5,510,594.00 was issued on 03/24/15 to Ownership.
Permit Details: Building 6 of 8 total buildings to be modernized (Building F, Stairways 11, 13, 15, 17, & 19, 37 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building D (building 6 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 6 of 8 total buildings to be modernized (Building F, Stairways 11, 13, 15, 17, & 19, 37 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building D (building 6 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064212015
A permit for the amount of $5,511,594.00 was issued on 03/24/15 to Ownership.
Permit Details: Building 5 of 8 total buildings to be modernized (Building B, Stairways 12, 14, 16, 18, & 20, 39 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building B (building 5 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 5 of 8 total buildings to be modernized (Building B, Stairways 12, 14, 16, 18, & 20, 39 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building B (building 5 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064202015
A permit for the amount of $5,511,594.00 was issued on 03/24/15 to Ownership.
Permit Details: Building 4 of 8 total buildings to be modernized (Building E, Stairways 1, 3, 5, 7, & 9, 38 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building E (building 4 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 4 of 8 total buildings to be modernized (Building E, Stairways 1, 3, 5, 7, & 9, 38 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building E (building 4 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064062015
A permit for the amount of $5,511,594.00 was issued on 03/23/15 to Ownership.
Permit Details: Building 3 of 8 total buildings to be modernized (Building A, Stairways 2, 4, 6, 8 & 10, 38 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building A (building 3 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 3 of 8 total buildings to be modernized (Building A, Stairways 2, 4, 6, 8 & 10, 38 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building A (building 3 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064052015
A permit for the amount of $5,510,549.00 was issued on 03/23/15 to Ownership.
Permit Details: Building 2 of 8 total buildings to be modernized (Building H, Stairways 35 & 33, 12 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building H (building 2 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, combined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 2 of 8 total buildings to be modernized (Building H, Stairways 35 & 33, 12 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building H (building 2 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, combined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
BLDM0064042015
A permit for the amount of $5,511,594.00 was issued on 03/23/15 to Ownership.
Permit Details: Building 1 of 8 total buildings to be modernized (Building D, Stairways 34 & 36, 12 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building D (building 1 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.
Permit Details: Building 1 of 8 total buildings to be modernized (Building D, Stairways 34 & 36, 12 Total Units for this permit). The project consists of the modernization of eight existing three-story plus basement, brick and concrete frame structures containing 268 apartment units. The work in building D (building 1 of 8) generally consists of: asbestos abatement, site work, building envelope improvements , Roof repairs, apartment interior improvements, paint and soffiting in common stair halls, new fire alarm and sprinkler systems, partial replacement of domestic water supply systems, installation of new mechanical systems, replacement of existing fan coil units, comined heat and power system, miscellaneous electrical upgrades as required for mechanical systems, and renovations of three (3) trash buildings.