Tampa International Airport Airside D
Update
01/26/23
Tampa International Airport Receives Three Bids to Construct New Airside
Three companies have submitted bids to construct the new Airside D at Tampa International Airport. The three companies are Austin Commercial LP, Hensel Phelps Construction Co., and
The Weitz Company LLC. The airport is expanding with the new $787.4 million terminal. Construction of Airside D is expected to start in 2024 and be completed in 2027. The contract will be awarded in August 2023. The new terminal will enable the Airport to serve an additional 13 million passengers by 2037. Airside D’s 16 gates will serve domestic and international flights, bringing TPA’s total gates to 72. The building will be about 563,000 square feet with vast concessions space, an outdoor terrace, state-of-the-art Customs and security facilities, as well as new screening, gate check-in and bag processing technologies.