Garage Foundation Work Begins at Fenway Center

Matt Edlen of Gerdling Edlen tells BLDUP via email that they have completed earthwork on the site and have started working on the garage foundation.  The $240 million Phase 1 of the project will feature 2 residential buildings totaling around 340,000 sf.  The underground garage now in process will include 200 parking spaces. Construction on Phase 1 is expected to be complete in early 2020.

Fenway Center 1

In total, the Fenway Center development will cost around $600 million and contain 1.1-million-square-foot of mixed-use space including approximately 550 residential units, 160,000 square feet of office space and over 50,000 square feet of retail.

Fenway Center 2