Project Progress: Interior Finishing

Architects CBT Architects
General Contractors Suffolk
Engineers VHB
Developers Gables Residential
Subcontractors Draper Elevator Interiors
Website https://gablesseaport.com/

About Gables Seaport (Waterside Place Phase 1B)

501 Congress Street, Seaport District, Boston, MA 02210

The project calls for a 23-story tower featuring 307 apartment residences ranging from studios to three-bedrooms. 62 residences will be "innovation units", and 15 residences will be designated affordable.

The tower will include 3,500 square feet of ground-floor retail and a second-floor parking garage with approximately 84 spaces. Waterside Place Phase 1B will be located steps from the MBTA Silver Line, minutes from Downtown Boston.

Construction Cost $157,000,000.00
Square Feet 325,000
Sector

Housing

Retail

Stories 23
Height (feet) 248
Start Date Feb 01, 2018
Topping Off Date Jun 02, 2019
In The Know
Sign up to unlock 30 extra data points.
Current Owner xxxxxxxxxxxxx
Owner Contact Info xxxxxxxxxxxxx
And More Sign up >>

Latest Updates


Feb 19, 2020

Construction Wrapping Up at Gables Seaport: Units Now Leasing

Read More >>


Dec 09, 2019

Gables Residential On Track to Deliver Superior Residential Experience in  Spring 2020

Read More >>


Oct 14, 2019

Interior Finishing Ongoing for Gables Seaport

Read More >>


Aug 15, 2019

Fire Alarm Permit Issued for Waterside Place Phase 1B

Read More >>


Jul 18, 2019

Window and Facade Install Nearly Complete for Waterside Place Phase 1B

Read More >>


Jun 02, 2019

Waterside Place Phase 1B Tops Off

Read More >>


May 03, 2019

Window Install Has Started for Waterside Place Phase 1B

Read More >>


Apr 17, 2019

This NPC is requesting a change of use for the remaining portion of the ground...

Read More >>


Jan 15, 2019

Framing Begins for Waterside Place Phase 1B

Read More >>


Oct 03, 2018

Work Begins on Interior Core for Waterside Place Phase 1B

Read More >>


Feb 25, 2018

Foundation construction begins at Waterside Place Phase 1B apartments in Seaport District

Read More >>


Jan 18, 2018

Waterside Place Phase 1B apartments in Seaport District secure construction financing and long-term ground lease

Read More >>


Dec 20, 2016

Waterside Place Phase 1B approaches Spring 2017 construction start

Read More >>


Jul 17, 2016

Waterside Place Phase 1B in Seaport District approved for construction

Read More >>


Mar 28, 2016

Notice of Project Change filed for Waterside Place Phase 1B

Read More >>


Dec 02, 2015

Letter of Intent filed for Waterside Place Phase 1B


A Letter of Intent to File...

Read More >>