Seaport Square Parcel P News

Jan 06, 2023

Glass Curtain Nearing Completion on Seaport Square Parcel P

Read More >>

Sep 30, 2022

Glass Installation Begins on Seaport Square Parcel P

Read More >>

Jun 03, 2022

Framing Tops Off on Seaport Square Parcel P

Read More >>

Apr 26, 2022

Framing Nearing Completion on Seaport Square Parcel P

Read More >>

Mar 18, 2022

Painting Begins on Under-Construction Parcel P in Seaport

Read More >>

Mar 02, 2022

Plumbing Fitout Underway on Seaport Square Parcel P

Read More >>

Feb 28, 2022

Framing Progressing on Seaport Square Parcel P

Read More >>

Nov 10, 2021

Fireproofing Underway on Parcel P in Seaport

Read More >>

Sep 24, 2021

Financing Secured for Under-Construction Parcel P in Seaport

Read More >>

Aug 03, 2021

Mitsubishi Selected for Elevator Installation at 400 Summer Street

Read More >>

Jun 14, 2021

Framing Begins on 400 Summer Street

Read More >>

Mar 21, 2021

Foundation Pour Complete for 400 Summer Street

Read More >>

Feb 03, 2021

Slurry Wall Bracing Underway on 400 Summer Foundation

Read More >>

Nov 24, 2020

Construction Continues at 400 Summer Street

Read More >>

Oct 14, 2020

$2.7M Plumbing Permit Pulled for 400 Summer St.

Read More >>

May 28, 2020

Site Work Back Underway at 400 Summer St

Read More >>

Mar 04, 2020

Site Work Begins on Seaport Square Parcel P

Read More >>

Feb 14, 2020

$236M Building Permit Pulled for 400 Summer Street

Read More >>

Aug 01, 2019

Foundation Medicine Leases 580,000 Square Feet at 400 Summer Street

Read More >>

Jul 18, 2019

WS Development Plans to Begin Construction on 400 Summer St. Later This Year

Read More >>